Notification of Planned Unavailability

ASEP

Revision

Date Published

Event Date

Expected Duration

Loss of
Volume 
(mcm/d)

Comments

Bacton SEAL221/10/18 12:0518/10/18~4 days6Export rates to slowly start to increase late this afternoon. Normal export levels not expected until Gas Day 22-Oct-2018
Bacton SEAL120/10/18 11:4518/10/18~ 3 days6Delay in ramping up export rates.
Bacton SEAL018/10/18 07:3318/10/18~ 2 days6.0Elgin Franklin flows ramping down for rig move. Works are weather dependent.
St Fergus112/10/18 07:3212/10/18 2.5Weather impacting works, wells re-opened this morning, normal rates expected later today
St Fergus010/10/18 07:4410/10/184 days4.5Laggan Tormore export rates reduced for a few days
Bacton SEAL3

08/08/18 15:28

30/07/1810 days10Elgin Franklin start up has commenced. Delivery at Bacton SEAL for Elgin Franklin is forecast for 18:00hrs tonight with a ramp up to normal rates for gas-day 9th August.
Bacton SEAL206/08/18 15:1730/07/189 days10

Restart is delayed. Elgin Franklin start up is currently forecast for 8th August. Ramp-up will be approximately 36 hours.

Bacton SEAL130/7/18 07:5630/07/188 days10Elgin Franklin export rates have started to ramp down. Delivery at the SEAL terminal for Elgin Franklin is forecast to stop at 1800 hrs today (30th)

 

Elgin Franklin start up is currently forecast for 7th August once the maintenance works is complete. Ramp-up will be approximately 36 hours.

Bacton SEAL029/07/18 18:2729/07/188 days10Elgin Franklin rates will start to ramp down tonight from midnight onwards for planned maintenance. 
Bacton SEAL002/07/18 09:0703/08/184 days10Elgin Franklin rates will ramp down on the 2nd August. Elgin Franklin rates will ramp up over 2 days following the maintenance works
NSMP SF528/06/18 05:1230/05/1829 days2.5Export has restarted Ramp up to normal rates will take 24-36 hours
NSMP SF427/06/18 10:1430/05/1829 days4Update: A further delay, export is expected today. Ramp up to normal rates will take 24-48 hours
NSMP SF326/06/18 12:0930/05/1828 days4Export expected later today. Ramp up to normal rates will take 24-48 hours
NSMP SF225/06/18 09:2430/05/1827 days4.0Start up process underway
NSMP SF221/06/18 18:5131/05/18 8.0Laggan Tormore flows to start from 1900 today, rates are expected to be close to normal for gas day 22-Jun-2018
NSMP SF121/06/18 16:0030/05/1826 days4.0Delayed restart of Alwyn
Bacton SEAL101/06/18 15:4104/06/183 days9.5 
Bacton SEAL031/05/18 21:4103/06/183 days9.5No gas export from Elgin Franklin due to the unavailability of liquid export route. The timings/duration may be subject to delay.
NSMP SF117/06/18 19:2631/05/1824 days11.5Revision due to expected restart being earlier than originally forecast. Timings remain subject to change.  Restart should be during 22nd June
NSMP SF006/04/18 16:0031/05/1829 days11.5ramp down on the 31st May
NSMP SF006/04/18 15:4230/05/1824 days4.0ramp down to start on the 29th
NSMP SF128/03/18 04:5928/03/181 day7.2Rates expected to increase over the course of the day
NSMP SF018/03/18 17:1828/03/181 day7Planned maintenance works affecting Laggan Tormore export rates (day 4 of 4)
NSMP SF227/03/18 22:2927/03/181 Day8.5 
NSMP SF127/03/18 05:0427/03/181 day11.5Revisin to forecast
NSMP SF018/03/18 17:1527/03/181 day10

Planned maintenance works affecting Laggan Tormore export rates (day 3 of 4)

NSMP SF126/03/18 05:1426/03/181 day12.2Revision to forecast 
NSMP SF018/03/18 17:1126/03/181 day9.0Planned maintenance works affecting Laggan Tormore export rates (day 2 of 4)
NSMP SF124/03/18 17:2025/03/181 day6.7Update to available capacity 
NSMP SF018/03/18 17:0825/03/181 day5.0Planned maintenance works affecting Laggan Tormore export rates for 4 days.
Bacton SEAL919/09/17 14:2930/07/17 18:0053 days11.0

Offshore production has restarted and ramp-up is in progress. A 2 day ramp up to normal rates within 48 hours.

Bacton SEAL818/09/17 15:2730/07/17 18:0052 days11.0

Start-up is in progress. A 2 day ramp up to normal rates is expected to commence from the 19th September 2017

Bacton SEAL717/09/17 17:2930/07/17 18:0051 days11.0

Due to delay estimated restart is now 18th September 2017.

Bacton SEAL614/09/17 15:1530/07/17 18:0050 days11.0

Due to delay estimated restart is now 17th September 2017.

Bacton SEAL513/09/17 15:5030/07/17 18:0048 days11.0

Due to delay estimated restart is now 15th September 2017.

Bacton SEAL408/09/17 16:3830/07/17 18:0047 days11.0Due to delay estimated restart is now 14th September 2017.
Bacton SEAL325/08/17 12:0430/07/17 18:0045 days11.0

Due to delay estimated restart is now 12th September 2017.

Bacton SEAL218/08/17 16:0830/07/17 18:0039 days11.0

Due to delay estimated restart is now 6th September 2017.

Bacton SEAL130/07/17 08:5430/07/17 18:0027 days11.0Offshore production has stopped earlier than forecast.    A 2 day ramp up to normal rates is forecast to commence on the 25th August 2017

 

Bacton SEAL030/06/17 15:1231/07/17 06:0027 days11.5

Ramp down of flows commencing 30th July 2017

2 day ramp up to normal rates will commence on the 26th August 2017

 

St Fergus225/06/17 08:4727/06/17 18:00~ 48 hours3ramp up ongoing, normal rates not expected for another 48 hours.
St Fergus124/06/2017 08:5224/06/17 ~6Offshore ramp is expected from midday, ramp up to normal rates not expected until Monday the 26th.
St Fergus028/04/17 12:2117/06/17 05:007 days9.0 
St Fergus016/04/17 16:3519/04/17 05:0024 hours8.5Rates will increase during gas day 20-Apr-2017 and rates will be normal again for gas day 21-Apr-2017
Bacton SEAL2

08/04/17 23:55

08/04/17 06:00 9.5

Due to a minor issue with the tide/weather situation, offshore flows ramp up is delayed to gas day 09/04/17.

Bacton SEAL107/04/17 15:4508/04/17 06:00 6

Offshore flows are currently reducing but Impact on gas day 07/04/17 is minimal. Offshore flows are forecasted to recommence during gas day 08/04/17.

Bacton SEAL403/04/17 18:0002/04/17 03:00 6Gas export has commenced from Elgin Franklin with slow ramp up as per procedures.
Bacton SEAL302/04/17 22:0702/04/17 03:00 11Ramp up delayed, duration unknown
Bacton SEAL202/04/17 18:2002/04/17 03:0020 hours8.5Ramp up delayed to 23:00 pm this evening.
Bacton SEAL102/04/17 10:1902/04/17 03:0014 hours6Flows currently at 0 mcm/day. Ramp up expected around 5 pm this afternoon.
Bacton SEAL329/03/17 07:4026/03/17  production restarted overnight. Flows at Bacton SEAL forecast to increase from 29-Mar-17 08:00, ramp up to previous rates over the next 2 days
Bacton SEAL228/03/17 08:4326/03/17unknown12Third party works complete. Start up tests ongoing, unknown at present when gas export will restart.
Bacton SEAL125/03/17 18:0226/03/1736-48 hours12.0

Offshore production ramp down on gas day 26th March. Offshore production is planned to stop for 36-48 hours A 2 day ramp up to previous rates is expected once the works are complete

Planned offshore reduction at Elgin Franklin (Bacton SEAL). The flow reduction is due to works being carried out by a third party on the oil export route. The duration and timing are subject to change.

Bacton SEAL019/03/17 09:0626/03/1736 hours12.6Offshore production ramp down on gas day 25th March. Offshore production is planned to stop for 36 hours starting 26th March. A 2 day ramp up to previous rates is expected once the works are complete
St Fergus208/02/17 06:5908/02/17 4Issue starting compressor delaying ramp up. Forecast to start compressor this morning with a ramp up to normal rates for gas day 09-Feb-2017
St Fergus107/02/17 07:2407/02/17 6Issue starting compressor delaying ramp up. Forecast to start compressor this morning with a ramp up to normal rates for gas day 08-Feb-2017
St Fergus003/02/17 11:4306/02/17 05:0012-18 hours11

11 mcm/day Flow loss estimated for 12-18 hours. Normal rates expected for gas day 07/02/17.

St Fergus218/12/16 12:0020/11/16 5.7

Ramp up ongoing, normal flows expected within 24-36 hours   

Bacton SEAL117/12/16 11:4014/12/16 4-5ramp up of flows expected over the next 24-48 hours 
Bacton SEAL012/12/16 07:3414/12/162-3 days5 
St Fergus114/11/16 09:5720/11/16 05:0028 days5.7Two days prior to the event flows will start to decrease. It will take two days after the event for flows to ramp back up to normal rates.   
St Fergus130/10/16 08:0030/10/16   Flows are ramping up, normal rates expected for gas day 31-Oct-2016
St Fergus028/10/16 20:1529/10/16 05:0024-36 hours5.0 
St Fergus024/10/16 20:5022/11/16 05:0026 days5.7Two days prior to the event flows will start to decrease. It will take two days after the event for flows to ramp back up to normal rates. 
Bacton SEAL 20/10/16 08:3020/10/1624 hours5 
St Fergus 06/10/16 19:42  7A further delay in increasing offshore flow.  Loss of 7.0 MCM.  At present it is unknown when flows will return to normal levels. 
St Fergus406/10/16 05:0506/10/16 7delay in increasing offshore flows, loss of around 7.0 MCM, normal production rates not expected until gas day 07-Oct-2016
St Fergus301/10/16 15:510210 - 05/10  Update of planned works in previous REMIT post at 2016-09-28 06:59:54   Offshore flow reductions resulting in reduced flows at NSMP St. Fergus   New dates below:   Gas Day 02-Oct-2016 ~ 4.0 MCM Gas Day 03-Oct-2016 loss increased by 10.0 MCM Gas Day 04-Oct-2016 expected loss reduced to 6.5 MCM Gas Day 05-Oct-2016 expected loss reduced to 5.0 MCM 
St Fergus228/09/16 06:5902/10 - 04/10  New dates below:   Gas Day 02-Oct-2016 3.0 MCM Gas Day 03-Oct-2016 loss increased by 11.0 MCM Gas Day 04-Oct-2016 expected loss reduced to 3.0 MCM 
St Fergus126/09/16 19:4329/09 -01/10  New dates below:   Gas Day 29-Sep-2016 3.0 MCM Gas Day 30-Sep-2016 loss increased by 11.0 MCM Gas Day 01-Oct-2016 expected loss reduced to 3.0 MCM 
St Fergus026/09/16 13:5227 - 29 September  Offshore flow reductions resulting in reduced flows at NSMP St. Fergus   Gas Day 27-Sep-2016  3.0 MCM, Gas Day 28-Sep-2016 loss increased by 11.0 MCM,Gas Day 29-Sep-2016 expected loss reduced to 3.0 MCM   
Bacton SEAL108/08/16 08:2808/08/16  Delay in restarting TOTAL E&P UK operated production, offshore production is forecast to restart this morning with delivery at Bacton SEAL a couple of hours later.   Ramp up of flows will take approximately 48 hours  
Bacton SEAL007/08/16 17:4307/08/16  Delay in restarting TOTAL E&P UK operated production, offshore production will not restart until gas day 08-Aug-16 ramp up of flows will take approximately 48 hours
St Fergus021/06/16 21:0022/06/16 05:007 days13-613-10 mcm/d reduction for 2 days and then 8-6 mcm/d reduction for 5 days.
Bacton SEAL219/05/16 08:0316/05/16  

SEAL flows now starting to increase, slow ramp up to previous rates over the next 24-48 hours

Bacton SEAL118/05/16 13:5616/05/16 9.0

Flow increase at SEAL not expected until Thursday (19/5) PM with a slow ramp up

Bacton SEAL016/05/16 12:1716/05/162 days9.0

flow loss of 9.0 MCM/D over the remainder of this gas day, duration expected to be 2 days

Bacton SEAL112/05/16 05:5011/05/16  

ramp up of offshore flows ongoing, Bacton SEAL flows to slowly increase over the course of the day

Bacton SEAL011/05/2016 05:5511/05/1624 hours5.0 
St Fergus113/04/16 20:4012/04/16 05:00 6.5

loss increased from 5.0 to 6.5 mcm/d from 2100 on the 13/04/2016. Duration until end of this gas day

St Fergus012/04/16 01:2712/04/16 05:002 days5 
Bacton SEAL510/03/16 14:1504/03/16  

Update, ramp up of flows at Bacton SEAL due to commence from 15:00hrs with normal rates by the end of the day..

Bacton SEAL410/03/16 11:2904/03/16  

Update: ramp up of flows at Bacton SEAL is unknown at present. Further update will follow once offshore flow has started

Bacton SEAL310/03/16 06:4704/03/16  Update: restart ongoing, ramp up of flows at Bacton SEAL now expected from midday today.
Bacton SEAL209/03/16 16:2404/03/16  Update: restart ongoing, ramp up of flows at Bacton SEAL now expected from 02:00hrs on the 10/03/16
Bacton SEAL109/03/16 11:2304/03/16  

Update: restart ongoing, ramp up of flows at Bacton SEAL expected from 20:00hrs tonight

Bacton SEAL002/03/16 11:4004/03/165 days9.0 
St Fergus417/02/16 15:2713/02/16 05:00  Update: offshore production resumed, rates increasing over the next 24 hours
St Fergus316/02/16 07:5013/02/16 05:00 5.0Update: unknown when offshore production will restart.  An update will be issued once production has restarted
St Fergus215/02/16 18:5513/02/16 05:00 5.0Update: no increase in rates for this gas day (15-Feb-2016)
St Fergus115/02/16 08:0513/02/16 05:00 5.0Update: rates expected to increase this afternoon
St Fergus012/02/16 21:0013/02/16 05:002 days5.0 
St Fergus021/10/15 09:1021/10/15 10:001 hour13 
St Fergus113/06/15 16:4514/6/201516 days6 
St Fergus030/04/2015 14:0015/06/201515 days7 
Bacton SEAL128/03/2015 09:1728/03/2015 09:15  Rates are slowly increasing
Bacton SEAL026/03/2015 06:5726/03/2015 07:0036 hours4.7Loss over the next ~6 hours
Bacton SEAL119/03/2015 21:5919/03/2015 22:00  Ramping up to normal levels over the next 24 hours
Bacton SEAL017/03/2015 11:0217/03/2015 11:002 - 3 days7.6Loss over the next 16 hours
St Fergus006/01/2015 20:0707/01/2015 06:006 hours12 
       

Notification of Unplanned Unavailability

ASEP

Revision

Date Published

Event Date

Expected Duration

Loss of
Volume 
(mcm/d)

Comments

Bacton SEAL17/10/18 16:3607/10/18  Rates will continue to ramp up over the next few hours. Normal delivery expected for gas day 08-Oct-2018
Bacton SEAL07/10/18 13:3207/10/18unknown11.2Flows for Elgin Franklin at Bacton SEAL are forecast to start to reduce from 1400 and stop at 1900 tonight. Restart time currently unknown.
Bacton SEAL024/08/18 07:0524/08/182 days2some wells taken offline, duration forecast at 2 days. 
Bacton SEAL121/08/18 20:2321/08/18 10Elgin Franklin delivery at Bacton SEAL to start from 2100 hours. Rates will ramp up overnight and are forecast to be at normal levels by 0900 on gas day 22-Aug-2018 
St Fergus121/08/18 11:3321/08/18 2Alwyn export has started ramp up ongoing, normal rates forecast for gas day 22-Aug-2018
Bacton SEAL019/08/18 22:2720/08/18 10Elgin Franklin offshore production is planned to stop by 0600 hrs on the 20-Aug-2018 due to Industrial action. Gas delivery of Elgin Franklin at Bacton SEAL is forecast to continue until 1500 hrs on the 20-Aug-2018. Restart of offshore flows of Elgin Franklin is not expected until midnight on the 21st. Flows at Bacton SEAL for Elgin Franklin should not be expected until Gas day 22nd August. A further message will be issued with a restart date / time of Elgin Franklin flows at Bacton SEAL
St Fergus019/08/18 22:1420/08/18 2Alwyn export is planned to stop due to Industrial action. Normal rates are expected by midday 21-Aug-2018 
Bacton SEAL114/08/18 15:2213/08/18 10

Elgin Franklin offshore production has restarted. Gas delivery of Elgin Franklin at Bacton SEAL is forecast to start from 17:00hrs today with a slow ramp up. Normal rates is expected for gas day 15-Aug-2018

St Fergus 013/08/18 09:2713/08/18 1.6Industrial action planned from midday today at Alwyn.   Normal rates expected for gas day 14th
Bacton SEAL013/08/18 09:1213/08/18 10Elgin Franklin offshsore production is planned to stop this morning due to Industrial action. Gas delivery of Elgin Franklin at Bacton SEAL is not expected to restart until the evening of the 14th. Normal rates are expected for gas day 15-Aug-2018 
Bacton SEAL325/07/18 15:5225/07/18 3Elgin Franklin delivery at SEAL has restarted and will continue to ramp up over the remainder of gas day 25-Jul-2018. Normal rates expected for gas day 26-Jul-2018
Bacton SEAL225/07/18 05:0925/07/18  Elgin Franklin restart process is underway. Elgin Franklin delivery at SEAL terminal has been delayed and is not now forecast to start until midday on the 25-Jul-2018. 
Bacton SEAL124/07/18 18:2424/07/18  Elgin Franklin restart process is underway. Elgin Franklin delivery at SEAL terminal is not now forecast to start until 0100 25-Jul-2018 
St Fergus 124/07/18 11:5524/07/18 2Alwyn rates increasing, normal rates expected for gas day 25-Jul-2018,
Bacton SEAL023/07/18 05:1023/07/18 10Elgin Franklin export from the platform has stopped due to Industrial action. Flows at Bacton SEAL for Elgin Franklin will reduce and are forecast to stop (for Elgin Franklin) at 1300 hrs on the 23rd July. Gas export of Elgin Franklin at Bacton SEAL is not expected to restart until the evening of the 24th normal rates are expected for gas day 25-Jul-2018 
St Fergus 023/07/18 04:5823/07/18 3.0Alwyn gas export to the NSMP Terminal has stopped due to Industrial action. Gas export from the NSMP Terminal for Alwyn is not expected to restart until some point during gas day 24-Jul-2018, normal rates are expected for gas day 25-Jul-2018. 
St Fergus 117/07/18 10:5017/07/18 2.3Production has restarted
St Fergus017/07/18 06:5017/07/18 3.2plant trip
Bacton SEAL115/07/18 19:2115/07/18 5.8Production from Elgin Franklin has restarted
Bacton SEAL015/07/18 14:3015/07/18 5.8Production from Elgin Franklin has stopped, duration unknown at this time, investigation ongoing
Bacton SEAL32806/18 21:4726/08/18 1.0Elgin Franklin offshore rates have been steady at normal levels for a few hours now. SEAL terminal delivery of Elgin Franklin will continue to slowly increase over the course of tonight and into tomorrow to this level.
Bacton SEAL228/06/18 05:2426/08/18 4.0Elgin Franklin rates at SEAL are slowly going to increase from the start of the gas day by 11am they are forecast to be at 6 MCM/D. 
Bacton SEAL127/06/18 12:1026/06/18 10Preparations to restart are ongoing, no gas export is expected this gas day from Elgin Franklin
Bacton SEAL026/06/18 14:0226/06/18unknown10Elgin Franklin share of the delivery at the SEAL terminal will start to reduce from 1400 hrs today. The Elgin Franklin share of delivery at the SEAL terminal is forecast to be zero from midnight. 

 

Elgin Franklin gas export has stopped. Restart date and time are currently unknown. An update on restart will be provided tomorrow

Bacton SEAL309/05/18 07:0407/05/1809/05/180

Elgin Franklin production back at normal levels.

Bacton SEAL208/05/18 06:3307/05/1809/05/180

Elgin Franklin ramp up slower than anticipated but will continue to slowly increase.

Ramp up to full rates will continue over the next 24 hours.

Bacton SEAL107/05/18 18:5907/05/1808/05/180

Restart on Elgin Franklin has commenced and rates will increase from midnight tonight onwards.

Slow ramp up to full rates expected over the next 14-15 hours.

Bacton SEAL007/05/18 05:5707/05/1808/05/1810

Due to an unplanned trip, gas export from Elgin Franklin is shut down.

Restart is forecast for within gas-day 7th May.

St Fergus406/05/18 16:2202/05/1806/05/180

Alwyn has restarted and is ramping up to normal levels. Third party availability issues have all been resolved.

Ramp up to full production will continue over the next 13 hours.

St Fergus304/05/18 22:5902/05/1806/05/184

Due to third-party unavailability, offshore production from Alwyn is still restricted. Laggan Tormore is ramping up to full rates.

Flow rates will increase over the next 7-8 hours.

St Fergus203/05/18 22:5202/05/1806/05/188

Due to third-party unavailability, offshore production from Alwyn and Laggan Tormore is restricted.

Due to a partial lifting of the current restrictions caused by the unavailability of the oil export route, flow rates will increase over the next 6-7 hours, gas export from the fields will be at approximately 50% of normal levels. Also full availability of the oil export route is now forecast for Sunday 6th May 06:00hrs.

St Fergus102/05/18 21:4002/05/1804/05/1813

Due to third-party unavailability, offshore production from Alwyn and Laggan Tormore is restricted.

Flow rates will continue to further reduce over the next 7 hours due to unavailability of the oil export route, gas export from the fields will be reduced to approximately 20% of normal levels.

St Fergus002/05/18 11:4502/05/1804/05/189

Due to third-party unavailability, offshore production from Alwyn and Laggan Tormore is restricted.

Bacton SEAL117/03/18 18:1918/03/18  

Forecast flows at SEAL for Elgin Franklin are forecast to reduce further as Stock levels rebuilt but will increase again from 2200 and be close to normal levels by end of this gas day. Estimated loss as an end of day figure 3.5 MCM

Compressor stop. Elgin Franklin production has restarted. Normal production levels for Elgin Franklin are expected by 2200 hrs tonight, stock levels have to be rebuilt in SEAL so normal delivery at Bacton SEAL terminal not expected until Gas Day 18-Mar-2018

Bacton SEAL017/03/18 13:3617/03/18 5Expected to start compressor later today. An update will be given later. If no restart Elgin Franklin flows at Bacton SEAL forecast to be zero from midnight
Bacton SEAL028/02/18 08:0928/02/18 2The below assumptions are based on the compressor not restarting during this gas day. It is hoped that the compressor can be restarted tonight.
Bacton SEAL410/02/18 08:0110/02/18 3Gas export rates from Elgin Franklin continue to ramp up to normal levels. Normal offshore production rates are forecast this morning. Elgin Franklin has to rebuild its stock position. The Elgin Franklin share of the delivery at SEAL terminal is expected to be at normal levels by the end of this gas day.
Bacton SEAL309/02/18 23:3009/02/18 8Delivery at the SEAL terminal for Elgin Franklin is forecast to start from around 0100 at a rate of 2.0 MCM/D, increasing to around 4.0 MCM/D at 0400. Rates will continue to increase. A further update will be issued during gas day 10-Feb-2018
Bacton SEAL209/02/18 07:3009/02/18 11At present restart time for Gas export from Elgin Franklin is unknown
Bacton SEAL108/02/18 07:4408/02/18 11At present restart time for Gas export from Elgin Franklin is unknown
Bacton SEAL007/02/18 14:2007/02/18unknown11Bacton SEAL flows to start reducing from 15:00hrs onwards. Elgin Franklin gas at SEAL forecast to stop around 21:00hrs. Restart time is unknown at present. 

Elgin Franklin gas export has had to stop due to a request to stop oil export.

Bacton SEAL028/12/17 07:2828/12/17 7 hours3.0Following a turbo expander trip, offshore flows were reduced, flows now increasing and forecast to be back to previous levels before the start of the next gas day. 
Bacton SEAL528/12/17 05:4928/12/17 1.5Offshore production is back to normal levels (technical capacity). Elgin Franklin delivery to Bacton SEAL will slowly increase over the course of the day to normal levels
Bacton SEAL427/12/17 12:4327/12/17 4Elgin Franklin delivery to the Bacton SEAL terminal is forecast to start from 1300hrs on Gas Day 27-Dec-2017 at a rate of 3 MCM/D, it will slowly increase over the afternoon to be around 7 MCM/D at 1700 hrs.
Bacton SEAL327/12/17 05:4827/12/17  Offshore Elgin Franklin production has resumed. Ramp up of gas flows will be linked to ramp up of oil rates. 
Bacton SEAL213/12/17 07:2812/12/17~3 weeks10Update: End Date revised, The duration of the shutdown is not known at present. 
Bacton SEAL111/12/17 17:2912/12/17n/a10Elgin Franklin gas export has had to stop due to the shutdown of the oil export pipeline. The duration of the shutdown is not known at present. Elgin Franklin flows at Bacton SEAL will stop from 2100 today. 
Bacton SEAL011/12/17 06:3211/12/17 6

Due to a restriction on the oil export route for Elgin Franklin, gas export from the field has been reduced by approx 60% from normal levels. The duration is unknown at the moment.

Bacton SEAL07/12/17 09:5607/12/17 4Due to a restriction on the oil export route for Elgin Franklin, gas export from the field has been reduced by 60% from normal levels. The duration is unknown at the moment. The impact is uncertain at the moment also.
Bacton SEAL426/11/17 20:41  4.9Normal rates expected during gas day 27-Nov-2017. Elgin Frankin flow rate at Bacton SEAL forecast to be 5.5 MCM/Day at 2100 and will slowly increase to end of this gas day.
Bacton SEAL326/11/17 09:4126/11/17 6.4Elgin Frankin restart is ongoing. Current forecast is that flows will increase at Bacton SEAL from 1500 on gas day 26th November. There will be a slow ramp up from 1500.
Bacton SEAL226/11/17 01:3726/11/17 10.4An update will be sent once this occurs. This message only relates to Elgin Franklin, not all flow at Bacton SEAL. 
Bacton SEAL125/11/17 23:05  3.0Update: The flows at Bacton SEAL will continue to reduce during the night as the gas landed for Elgin Franklin at Bacton SEAL is only coming from pipeline stock. This message only relates to Elgin Franklin, not all flow at Bacton SEAL. As an end of day value the loss at Bacton SEAL is approximately 3.5 MCM. The original flowrate for today was 10.4 MCM, currently it's around 7 MCM/Day and by 0500 it's forecast to be only 1 MCM/D . A new message for gas day 26-Nov-2017 will be posted later.
Bacton SEAL025/11/17 18:2225/11/17 3.0Investigation ongoing. Initial estimate will be offshore production restarting 0600 26/11/17. There will be a ramp up period for offshore and then an increase in flows at the Bacton SEAL terminal. A further message will be posted when more is known
Bacton SEAL426/10/17 05:1026/10/173-4 days3.2Offshore flows are forecast to remain at 7.5 MCM/D into the weekend when they will increase to technical capacity
Bacton SEAL325/10/17 19:5025/10/17 7.7Flows at Bacton SEAL to slowly increase from 2000 (Gas day 25-Oct-2017)
Bacton SEAL225/10/17 05:1425/10/17 10.7The plant is being prepared for restart. Offshore gas export is not expected until late afternoon, with a slow increase in flows at Bacton SEAL from this evening. Forecast below assumes worst case of no restart today, an update will be sent when platform restarts
Bacton SEAL124/10/17 05:1224/10/17 10.7Restart time unknown
Bacton SEAL023/10/17 19:3323/10/17 5Offshore production has stopped, cause currently being investigated.
St Fergus307/9/17 11:27

06/09/17

 4.6

Ramp up will continue over gas day 07-Sep-2017.  Normal rates expected for gas day 08-Sep-2017

St Fergus207/0917 05:0706/09/17 6.7Offshore flows have restarted.   Ramp up will continue over gas day 07-Sep-2017.  Normal rates expected for gas day 08-Sep-2017
St Fergus106/09/17 14:4406/09/17 12:00 7.4Impact on within day increased.
St Fergus006/09/17 11:5206/09/17 12:00 5.7Currently in process of restarting offshore flows. Normal rates expected for gas day 07-Sep-2017
St Fergus316/07/17 20:2015/07/17 11:00 0Production now back at full rates.
St Fergus216/07/17 06:5415/07/17 11:00unknown9Restart commenced gas-day 16th July, ramp up to full rates over the next 12 hours.
St Fergus115/07/17 21:3515/07/17 11:00unknown9Restart is not currently forecast until end of gas-day 15th July/start of gas-day 16th July.
St Fergus015/07/17 12:1215/07/17 11:00unknown9Duration currently unknown.
Bacton SEAL216/06/17 15:2114/06/17 08:00 2.0Maintenance works completed earlier than planned. Offshore rates ramping up to previous levels over the next four hours
Bacton SEAL115/06/17 07:5914/06/17 08:00~ 7 days4.5estimated at 7 days
Bacton SEAL014/06/17 08:2314/06/17 08:00~2 days5.0Duration unknown at present estimated at 2 days
Bacton SEAL408/03/17 12:2806/03/17 14:55 2

Ramp up ongoing. Normal Flow rates expected before the end of gas day 08/03/17.

Bacton SEAL307/03/17 17:4406/03/17 14:55 5

Ramp up delayed until midday tomorrow (gas day 08/03/17).

St Fergus207/03/17 17:26 07/01/17 01:00 4

Ramp up ongoing. Normal rated expected for gas day 08/03/17.

Bacton SEAL207/03/17 09:2306/03/17 14:55 4

Flows ramping up. Normal rates expected for gas day 08/03/17.

St Fergus107/03/17 06:5707/01/17 01:00 5

Unplanned Offshore Flow Reduction at NSMP St Fergus Terminal (Greater Laggan Tormore). Duration unknown.

Bacton SEAL106/03/17 16:3606/03/17 14:55 5

Unplanned Offshore flow reduction at Bacton SEAL terminal (Elgin Franklin). Flow loss of 9 mcm/day other the next 12 hours. Duration unknown.

St Fergus206/03/17 15:5106/03/17 01:00 4

Ramp up ongoing. Flows are increasing and normal rates are expected from gas day 07/03/17.

St Fergus106/03/17 07:1506/03/17 01:00 5

Unplanned Offshore flow reduction at NSMP St Fergus Terminal (Greater Laggan Tormore). Duration Unknown

St Fergus219/02/17 09:5114/02/17 16:00 0

Flows ramped up as planned.

St Fergus115/02/17 07:4514/02/17 16:00 6

Flow reduction of 6 mcm/day. Ramp up ongoing, flows should be back to normal before the end of gas day.

St Fergus3

12/02/17 11:56

11/02/17 15:00 7

Ramp up to full production ongoing

St Fergus212/02/17 06:5611/02/17 15:00 11

Flow reduction of 11.0 MCM/D over the remainder of the gas day, duration unknown

St Fergus111/02/17 17:4811/02/17 15:00 4.5Duration unknown
Bacton SEAL804/02/17 10:4630/01/17 08:00 0

Flows at Bacton SEAL back to normal.

Bacton SEAL703/02/17 15:5130/01/17 08:00 3

Offshore production ramping up. Flows at Bacton SEAL to slowly increase over the course of this gas day.

Bacton SEAL630/01/17 06:5130/01/17 08:00 5Offshore production has tripped. On restart production will be limited to 5 MCM for unknown period 
Bacton SEAL519/01/17 11:4413/01/17 18:30 4.5

Ramp up on hold, duration unknown. Update will be sent once production increases.

Bacton SEAL417/01/17 09:36 13/01/17 18:30 6Ramp up on hold. Export rate is around 6 mscm/d and will remain at this value for at least 2 days..
Bacton SEAL316/01/17 10:4613/01/17 18:30 6